Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Use your knowledge of the climate zones of the United States and Canada to interpret the map above. Look at the map key. What is the correct heading for zone tw
There is a bag filled with 5 blue and 4 red marbles. A marble is taken at random from the bag, the colour is noted and then it is replaced. Another marble is ta
Frankie wants to build a path from one corner of his yard to the opposite corner. His yard measures 20 ft. x 32 ft. What will be the length of his path to the n
Can somebody PLEASE help me with this :) ??
X/-4 -(-8)=12 16 80 -80 -16
is samus better than wario in smash ultimate
You are presented with several wires made of the same conducting material. The radius and drift speed are given for each wire in terms of some unknown units r a
What was Lincoln's plan for Reconstruction, and why did Radical Republicans oppose it?
y varies inversely with x. If y = 13 and k (the constant of variation) = 156, what is x?Round to the nearest whole number, if necessary.​
Answer this please thanks