is A and B can do a piece of work in 6 and 12day respectively how m
any part of work can they do in 4 day​

Respuesta :

wolf1728
wolf1728 wolf1728
  • 12-08-2021

Answer:

6 * 12 / (6+12) = 72 / 18

If they work together they can finish in 4 days.

Source: http://www.1728.org/work.htm

Step-by-step explanation:

Answer Link

Otras preguntas

When you talk about age in Spanish do you use the verb "tengo". True False
A scientist monitors the contents of five duck nests in parks, five duck nests in zoos, and five duck nests in the wild during the spring and summer for three y
19 is 19% of?HELP????????????????????
What do authors of fiction stories teach readers? A fact of science A message about life How to do something Where to get something
Create a parenthetical citation for the following information. Be careful! Remember, your spacing and punctuation must be exact. page 15 of the book Twain’s Boy
Abby counts 12 large boxes and 18 small boxes of pencils in the supply cabinet. Each large box contains 144 pencils. Each small box contains 24 pencils.Estimate
The table below shows the distance d(t) in feet that an object travels in t seconds. t d(t) (second) (feet) 1 15 2
Satire may be brutal and scathing or gentle and good-natured, but it always involves a criticism that remains ______ rather than explicit.
How many ounces of trail mix are in a bag that weighs 0.5675
What condition did aslan place on meeting with the white witch