hamsterhannah2700 hamsterhannah2700
  • 04-06-2020
  • Mathematics
contestada

A plumber laying 500meters of drain pipe requires 20men working for 10days. What length in meters would be laid by 50men in 5days, if they all work at same rate?

Respuesta :

onyebuchinnaji
onyebuchinnaji onyebuchinnaji
  • 06-06-2020

Answer:

50men working in 5days will lay 100 meters

Step-by-step explanation:

If 20men working for 10days lays 500meters

then, 1 man will lay 10,000 meters in 10 days

also, 1 man will lay 1000 meters in 1 day

If 1 man lays 1000 meters in 1 day,

Then, 50 men will lay (1000 meters / 50 );  20 meters in 1 day

also, the same 50 men will lay (20 meters x 5days); 100 meters in 5 days.

Therefore, 50men working in 5days will lay 100 meters

Answer Link

Otras preguntas

41/50 is closer to 9/11 or 10/11 and explain
what does a scientist do if I a hypothesis is supported
FIRST PERSON TO ANSWER GETS BRAINIEST ANSWER SO HURRY QUICK QUICK FIRST PERSON TO ANSWER GETS BRAINIEST ANSWER SO HURRY QUICK QUICK FIRST PERSON TO ANSWER GETS
Is initial velocity can be negative?
How do you calculate velocity?
which of the following actions reflects the political philosophy expressed in the declarations of independence
Why the right kidney sit lower than the left?
write the number in two other forms 7.632
Which of the following were changes America experienced during the second half of the nineteenth century? More then one answer a war with Great Britain major t
A video last 6.44 minutes. About how long does the videonlast, round to the nearest minute?