  • 15-03-2024
  • Mathematics
contestada

a and b can complete a work in 13 and 17 days. a startd working and they work alternately one day each. in How many days the work will be completed

Respuesta :

Otras preguntas

how are continents and tectonic pates related
Explain why animals must eat food, but plants do not have to.
solving fraction equations:  Write the solution in simplest form 6 1/4 = z + 1 5/8
what interaction between American Indians and European colonists was most important.? why?
What are some facts about Themistocles of Greece?   I know he was an Athenian general and politician. I have a project for history where I need to act JUST LIKE
a single molecule has at least how many atoms
On a map what do black dots usually represent?
Explain why animals must eat food, but plants do not have to.
What's the scientific name of a flathead bullhead catfish?
A park is in the shape of a rectangle 2 miles long and 1.5 miles wide. How much shorter if you walk diaganolly across the park rather than along two sides?