if structural steel installed in 2.75 floors of a building 2 3/8 day , how long will it take to install steel in 11 floors

Respuesta :

gentlebiker
gentlebiker gentlebiker
  • 01-08-2017
I will take 9.5 days, to install steel in 11 floors.
Answer Link

Otras preguntas

They aim to kindle interest and to direct the activity of the awakened student along sound lines.The word kindle in this sentence conveys a sense of (5 points)O
EASY QUESTION WILL GIVE BRAINLIEST
Isabel drove 864 miles in 12 hours. At the same rate, how many miles would she drive in 7 hours?
A historian is interested in conducting a deep analysis on the American stock market crash of 1929 in an effort to understand how economies shrink and grow over
Mohan is selling cookies at the economics fair. As he decides how to package the cookies, he finds that when he bags them in groups of 4, he has 3 left over. Wh
The function N(X) = 90(0.86)* + 69 can be used to predict the temperature of a cup of hot chocolate in degrees Fahrenheit after x minutes. What is the approxima
Don't be late "he advised us. change to indirect speech​
Triangle ABC was dilated using the rule Y, 5/4. FCA is equal to eight what is C’A’ 10 units 12 and 16 units 20 units
During the end-of-period processing, which of the following best describes the logical order of steps? preparation of income statement, adjusted trial balance,
What number is 22 ten thousands of 1 1/2